Production
- Achieve budgeted production from our uranium and fuel services segments.
|
Achieved
- Our share of U3O8 production was 21.9 million pounds, or 99% of plan, and we produced 14.2 million kgU at fuel services, or 99% of plan.
|
McArthur River
- Implement productivity improvements to maintain planned production during mining zone transitions.
|
Achieved
- Made productivity improvements on cycle times, and changed the sequencing of the raises in zone 2, panel 5. Mitigated the risk to production in 2013 associated with the transition to the upper mining area of zone 4.
|
Financial measures
Corporate performance
- Achieve budgeted net earnings and cash flow from operations (before working capital changes).
|
Exceeded
- Adjusted net earnings1 were $447 million, 20% higher than budget. Cash flow from operations (before working capital changes)1 was $717 million, 22% higher than budget.
|
Costs
- Achieve budgeted unit operating costs and corporate support costs.
|
Achieved
- Actual consolidated unit operating costs were in line with budget. Unit operating costs for uranium were $20.46 or 3% higher than budget and unit operating costs for fuel services were 2% lower than our budget of $17.11 per kgU. For the purposes of calculating performance on this objective, unit costs are weighted 70% for uranium and 30% for fuel services. Direct administrative expenses (corporate support costs) at year-end were 3% better than budgeted costs of $168 million. Our minimum target was to achieve budgeted unit costs on a consolidated basis.
|
Growth
- Meet regulatory project milestones and stage gate assessments on projects that support our Double U growth strategy.
|
Achieved
- Licence renewal applications were submitted for McArthur River, Key Lake and Rabbit Lake sites. Draft Environmental Impact Statements were submitted for the Millennium project, Key Lake extension project, and Eagle Point water management. Licence renewals were received for Blind River refinery, Port Hope conversion facility and Cameco Fuel Manufacturing. Engineering, procurement and construction management (EPCM) approach rolled out for McArthur River expansion, Millennium and the Port Hope Vision in Motion projects, and EPCM negotiations completed and firms retained. In Q4, we adjusted our growth strategy down from 40 million to 36 million pounds U3O8 by 2018.
|
Cigar Lake
- Advance the project towards startup in 2013 by successfully completing critical activities planned for 2012.
|
Achieved
- Completed the sinking of shaft 2 to its final depth of 500 metres and began installing shaft infrastructure. Assembled the first jet boring system unit underground, moved it to a production tunnel and began preliminary commissioning and system testing. Cigar Lake is a challenging deposit to mine. Completion of these critical milestones requires careful planning and deliberate execution.
|
Inkai
- Advance block 3 mineral resource delineation drilling and complete the test leach facility.
|
Partially achieved
- Received regulatory approval for the detailed block 3 delineation and test leach work programs. Continued to advance block 3 mineral resource delineation, started technological drilling of test wellfields, continued infrastructure development and started construction of a test leach facility.
|
- Receive approval to increase annual production from blocks 1 and 2 to design capacity of 5.2 million pounds per annum (100% basis). Continue to advance our longer-term objective of receiving approval to double annual production from blocks 1 and 2, extend the lease terms and secure block 3 mining rights.
|
Partially achieved
- We continue to await government approval of an amendment to the resource use contract to increase annual production from blocks 1 and 2 to 5.2 million pounds per year (100% basis).
- We signed a binding memorandum of agreement with our partner setting out the framework to increase annual production to 10.4 million pounds (100% basis), to extend the term of Inkai's resource use contract, and to co-operate on the development of uranium conversion capacity, with the primary focus on uranium refining. Implementation of the MOA in this complex and developing regulatory environment is subject to further agreements and receipt of all necessary Canadian and Kazakhstan government approvals.
|
Kintyre
- Continue to advance project evaluation in 2012 and decide if we will proceed to feasibility.
|
Achieved
- We drill tested ten additional prospective areas on the property in 2012 and no additional resources were identified. We completed the prefeasibility study and decided not to proceed with the feasibility study at this time due to challenging project economics.
|
Exploration and innovation
- Replace mineral reserves and resources at the rate of annual U3O8 production based on a three-year rolling average.
|
Achieved
- Over the last three years, mineral reserves decreased by 13.5 million pounds compared to production of 67.2 million pounds, measured and indicated resources increased by 104.4 million pounds and inferred resources decreased by 67 million pounds. On average, production was replaced and exceeded by nearly 8 million pounds per year in each of the last three years (2010 to 2012). Replacing our reserves and resources is fundamental to our long-term success.
|
Capital project management
- Deliver capital projects planned for completion in 2012 within budget and on schedule.
|
Partially achieved
- The 165 capital projects that closed in 2012 were on schedule but 11.9% over our budget of $300 million.
|